摘要: 辐射控制区建立是核电站具备核燃料装载的必要条件之一,也是电站辐射防护部门在移交接产阶段最为重要的一项任务。本文通过对华龙一号核电机组辐射控制区建立过程中的特点和难点的介绍,结合CPR、EPR机型的相关经验,从“控制区边界”“信息标牌”“监测系统”“功能房间”“通风状态”“厂房清洁”“防护物资”等7个关键项目,对辐射控制区建立的相关工作进行总结分析。对影响后期控制区正常运行的相关事项,如BAX房间功能位置调整及装修改造等,进行了着重说明并提供了解决方案。

关键词: 核电厂, 华龙一号核电机组, 辐射控制区

Abstract: The establishment of a radiation control area is one of the necessary conditions for nuclear power plants to load nuclear fuel, and it is also the most important task for the radiation protection department of a power plant during the handover phase. This paper introduces the characteristics and difficulties of Hualong One reactor type in the process of establishing a control area. At the same time, combined with relevant experience of CPR and EPR models in the process of establishing a control area, this paper focuses on analyzing the key items of the establishment of seven controlled areas, such as "control area boundaries", "information signs", "monitoring systems", and "material preparation", and makes a comprehensive summary of the work related to the establishment of control area. The paper discusses the relevant matters that affect the normal operation of the control area in the later stage, such as the adjustment of the functional position and renovation of the BAX room, and provides solutions for reference. In addition, the paper also explains some typical situations that may be overlooked during the establishment of the control area and lead to unplanned accidental exposure risks, such as the original design defects of the grille door of the outer ring corridor of the fuel transfer channel, which leads to incomplete isolation during fuel transfer.

Key words: nuclear power plants, Hualong-1, radiation control area